Bella Vida Construction Corner Post date August 19, 2025 Construction Corner includes the latest updates on construction progress at Bella Vida, keeping you informed as our beautiful new San Antonio senior living community takes shape. February Construction Progress View from Second Floor of Independent Living Building Memory Support Building and The Villas in background Independent Living Villa: Installation of roofing, weather barriers, windows and mechanical, electrical and plumbing lines brought in Underground water utility installation for Memory Support and Independent Living Memory Support interior: Fire protection, mechanical systems and electrical installations Memory Support interior: Fire protection, mechanical systems and electrical installations February 2026 January Construction Progress Framing at The Villas Villa residence entrance, roof truss installation View from 2nd floor of Independent Living Independent Living Memory Support January 2026 December Construction Progress First delivery of wood framing materials First delivery of wood framing materials Storm drain piping Slabs with blue post-tension cables for added strength and crack resistance; Crawler crane in background. Slab poured and walls marked for Memory Support Crews working on mockup, a full-scale sample section allowing the team to test materials and design before actual construction begins BV Site – January 2025 BV Site – December 2025 November Construction Progress Site wall construction Concrete finishing Vapor barrier installation at The Villas Storm drain utility installation along main drive Wall between Memory Support building and Independent Living building – texturing panels Finished texture wall panel October Construction Progress Crews are preparing to pour the floor above. Forms are being set for flooring in back-of-house spaces and teammate breakroom. Reinforcing cables and steel to strengthen concrete slab in parking area. Mechanical, electrical and plumbing work for The Villas. Earth moving, utility installation and site wall construction underway at the southern end of the development. January 2025 October 2025 September Construction Progress Plumbing pipes at the Villas Underground Utility installation underway for Independent Living Independent Living building is taking shape. January 2025 September 2025 August Construction Progress Wall installation between Memory Support garden and Independent Living tower On site tower crane helping shape the next level. Columns and walls going up in the lower-level parking garage of the Independent Living tower. January 2025 August 2025 ← Older Posts Newer Posts →